Dole
Terminal Development
Dole
Terminal Development Project - Port of Wilmington, DE
The
Dole Corporation, located in the Port of Wilmington,
Delaware, recently constructed a refrigerated container
storage to increase their fresh fruit handling volume
while operating in a limited amount of space. Dole’s
property was previously used for wheeled-chasis parking
only. Although the ability to provide these parking
spaces is important, Dole’s valuable property
was not maximized. Dole also acquired an adjacent parcel
from the Port to accommodate the expansion.
The
proposed storage facility consists of an 1100 foot long
by 80 foot wide, concrete runway that provides a platform
for stacked containers and intermediate scaffolding.
The facility is conveniently located near the dock area
of the Port, providing a short path for container movement
from the ships to the storage area.
The
soils underlying the Dole property are primarily
unconsolidated
organic silts and clays. Soils in the adjacent parcel
are composed of gypsum that had been exposed to
the
constant loading of gypsum stockpiles placed by the
previous owners. Since the proposed facility would
span
the two different soil conditions, and a high degree
of differential settlement was anticipated, a temporary
surcharge embankment was placed on the unconsolidated
region to accelerate the settlement. Wick drains
were
driven through the embankment to further accelerate
the settlement. Due to the equipment tolerances,
discontinuities
in the finished pavement surfaces are not acceptable.
These settlement conditions and operational considerations
were incorporated into the pavement and concrete designs.
The
Dole facility remained in operation throughout the duration
of the project. Considerations were taken to phase the
project so the impact to normal operations was minimized
while maintaining the construction schedule required
by the Port and Dole.
Dole
purchased a Rubber Tyred Gantry (RTG) crane to move
the containers within the facility. The containers will
also be moved by top-pick loaders. In order to accommodate
the immense wheel loads of the RTG and the loading of
the containers, the runway was designed as a double-reinforced,
16“ thick, concrete mat foundation. Raised pedestals
were provided for the three-tier scaffolds that hold
the refrigerated outlet plugs and allow workers to move
throughout the facility. Twenty scaffolds were located
in the facility with forty-foot spaces separating them.
An
employee parking lot and access road were provided for
Dole near the administration building. Additional paving
was constructed on the site to provide areas for truck
circulation and container movement. Four different paving
sections were designed for the site in accordance with
the varying loads and soil conditions.
Grading
of the site was designed in accordance within the tolerances
of the RTG and top pick loaders while providing adequate
drainage. New inlets were located throughout the site
and runoff is conveyed through a closed system to the
stormwater management facility. Large diameter, heavy-duty
concrete pipe was designed for the site due to the limited
cover over the pipes and high loads. Approximately 1000
feet of water main was relocated under this project.
The
stormwater management facility was designed as an 850-foot
long underground stone reservoir located in an existing
drainage swale. The drainage swale was heavily littered
with trash and construction debris and existed as unused
space in the Port. The facility includes a network of
perforated PVC pipes and sumped catch basins to treat
runoff from the new construction and additional areas
of the Port. The facility is covered with a layer of
compacted stone enabling the Port to use the space for
future storage.
|