WBCM provided complete turn key Design-Build services for the expansion of Yara’s Baltimore terminal to accommodate the production of diesel exhaust fluid (DEF). Major upgrades to the terminal included a new deionized, reverse-osmosis water treatment system, two storage tanks with dedicated high-accuracy blending pumps, a new air receiver with dryer for an existing compressed air system, and modifications to the existing truck load-out station to accommodate the new processes. Upgrades were phased to maintain terminal operations while minimizing outages.

WBCM provided complete construction services and pro-actively obtained all required permits to ensure that construction was completed in time to meet seasonal business demands.

Client
Yara International
Service(s) Provided
Process Engineering, Industrial Engineering, Structural Engineering, Marine Engineering, Civil Engineering, Surveying, Permitting, Construction Management
Location
Baltimore, MD